About Project

C1
dust collector
Metal (tons) 2040
6800 inch piping
Cabling 17000 m
The duration of the work is 6 months
Installation: MMT company
C2
Furnace
Metal (tons) 4960
13000 inch piping
Cable laying 61090 m
The duration of the work is 10 months
installation: EOS company
C3
CCM
Metal (tons) 2408
23000 inch piping
Cable laying 36075 m
The duration of the work is 12 months
Installation: MMTE company

Complex Strategy Plan

electrical post connection 400

پیشرفت پروژه

Steel making phase one

A furnace with a capacity of 1.5 million tons and a casting line with a variety of wide slab products with a capacity of 1.2 million tons.

Steel making phase two

A furnace with a capacity of 1.5 million tons and a casting line with a variety of wide slab products with a capacity of 1.2 million tons.

Steel making phase three

A furnace with a capacity of 1.5 million tons and two casting lines with a variety of billet and bloom products with a capacity of 1.2 million tons each.

Sponge iron mega module phase one

2 million tons per year

Sponge iron mega module phase two

2 million tons per year

Phase three sponge iron mega module

2 million tons per year

pelletizing

5 million tons per year

Sheet rolling unit

proportional Capacity

Profile rolling unit

proportional Capacity

More Information

Visual report of the project

Visual report of the progress of the project in February 2018

Jahan Ara Arvand Steel Company project teaser

In the horizon of the landscape

-Dynamic and innovative in the production of distinctive steel products.

-Leader in the country and region.

-Playing a role in improving the quality of life of the people in the place of activity.

-Environment lover.