Project Progress Report

AJS Co.

2022-7-22

Summary of project performance Up to 2022-7-22

AJS Company’s has achieved a progress of 98.81% in total, the details of the progress of the first phase of the casting project in the Engineering with 100%, and in the procurement  the progress has been 99.94%. Also, this project has achieved progressed 100% in construction and 98.63% in erection activities. Also in testing and commissioning has been achieve progress 95.11%, and in training 30.00 %. Also, there has been 100% progress in the Electricity Substation Project, and achieve progress 92.42% in the RO department and also progress in the gas project has been 100%.

» More information

2022-6-10

Summary of project performance Up to 2022-6-10

AJS  Company’s has achieved a progress of 98.26% in total, the details of the progress of the first phase of the casting project in the Engineering with 100%, and in the procurement  the progress has been 99.38%. Also, this project has achieved progressed 100% in construction and 97.93% in erection activities. Also in testing and commissioning has been achieve progress 91.32%, and in training 30.00 %. Also, there has been 100% progress in the Electricity Substation Project, and achieve progress 92.16% in the RO department and also progress in the gas project has been 100%.
»More information

2022-5-27

Summary of project performance Up to 2022-5-27

AJS Company’s has achieved a progress of 98.09% in total, the details of the progress of the first phase of the casting project in the Engineering with 100%, and in the procurement  the progress has been 99.37%. Also, this project has achieved progressed 100% in construction and 97.63% in erection activities. Also in testing and commissioning has been achieve progress 89.30%, and in training 26.50 %. Also, there has been 100% progress in the Electricity Substation Project, and achieve progress 91.89% in the RO department and also progress in the gas project has been 100% » More information

2022-4-15

Summary of project performance Up to 2022-4-15

AJS  Company’s has achieved a progress of 97.02% in total, the details of the progress of the first phase of the casting project in the Engineering with 100%, and in the procurement  the progress has been 98.41%. Also, this project has achieved progressed 100% in construction and 96.50% in erection activities. Also in testing and commissioning has been achieve progress 77.47%, and in training 26.50 %. Also, there has been 100% progress in the Electricity Substation Project, and achieve progress 89.78% in the RO department and also progress in the gas project has been 100%. » More information

2022-4-8

Summary of project performance Up to 2022-4-8

AJS Company’s has achieved a progress of 96.92% in total, the details of the progress of the first phase of the casting project in the Engineering with 100%, and in the procurement  the progress has been 98.41%. Also, this project has achieved progressed 100% in construction and 96.34% in erection activities. Also in testing and commissioning has been achieve progress 75.54%, and in training 26.50 %. Also, there has been 100% progress in the Electricity Substation Project, and achieve progress 89.76% in the RO department and also progress in the gas project has been 100% » More information

2021-12-31

Summary of project performance Up to 2021-12-31

AJS Company’s has achieved a progress of 94.33% in total, the details of the progress of the first phase of the casting project in the Engineering with 100%, and in the procurement  the progress has been 97.63%. Also, this project has achieved progressed 99.95% in construction and 91.71% in erection activities. Also in testing and commissioning has been achieve progress 41.21%, and in training 15 %. Also, there has been 100% progress in the Electricity Substation Project, and achieve progress 88.93% in the RO department and also progress in the gas project has been 100%.

»more information

2021-09-10

Summary of project performance Up to 2021-09-10

AJS Company’s has achieved a progress of 90.81% in total, the details of the progress of the first phase of the casting project in the Engineering with 100%, and in the procurement  the progress has been 97.48%. Also, this project has achieved progressed 99.78% in construction and 86.34% in erection activities. Also in testing and commissioning has been achieve progress 21.69%, Also, there has been 99.26% progress in the Electricity Substation Project, and achieve progress 84.26% in the RO department and also progress in the gas project has been 100%.

» More information.

2021-05-07

Summary of project performance Up to 2021-05-07

AJS Company’s has achieved a progress of 87.85% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 92.89%. Also, this project has achieved progressed 99.56% in construction and 79.04% in erection activities. Also in testing and commissioning has been achieve progress 6.48%, Also, there has been 98.22% progress in the Electricity Substation Project, and achieve progress 73.72% in the RO department and also progress in the gas project has been 100%.

» more information.

2021-04-16

Summary of project performance Up to 2021-04-16

AJS  Company’s has achieved a progress of 87.45% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 92.65%. Also, this project has achieved progressed 99.56% in construction and 77.85% in erection activities. Also in testing and commissioning has been achieve progress 6.04%, Also, there has been 98.12% progress in the Electricity Substation Project, and achieve progress 71.07% in the RO department and also progress in the gas project has been 100%.

» more information

2021-04-09

Summary of project performance Up to 2021-04-09

AJS  Company’s has achieved a progress of 87.21% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 92.65%. Also, this project has achieved progressed 99.56% in construction and 77.15% in erection activities. Also in testing and commissioning has been achieve progress 3.38%, Also, there has been 98.07% progress in the Electricity Substation Project, and achieve progress 70.76% in the RO department and also progress in the gas project has been 100%.   » more information

2021-04-02

Summary of project performance Up to 2021-04–02

AJS Company’s has achieved a progress of 87.08% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 92.63%. Also, this project has achieved progressed 99.56% in construction and 76.80% in erection activities. Also in testing and commissioning has been achieve progress 2.29%, Also, there has been 98.05% progress in the Electricity Substation Project, and achieve progress 70.52% in the RO department and also progress in the gas project has been 100%.   »more information

2021-02-26

Summary of project performance Up to 2021-02-26

AJS Company’s has achieved a progress of 86.15% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 92.63%. Also, this project has achieved progressed 99.56% in construction and 72.85% in erection activities. Also in testing and commissioning has been achieve progress 1.48%, Also, there has been 97.77% progress in the Electricity Substation Project, and achieve progress 69.55% in the RO department and also progress in the gas project has been 100%.

»more information

2021-02-19

Summary of project performance Up to 2021-02-19

AJS  Company’s has achieved a progress of 85.74% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 92.15%. Also, this project has achieved progressed 99.52% in construction and 72.28% in erection activities. Also, there has been 97.76% progress in the Electricity Substation Project, and achieve progress 69.04% in the RO department and also progress in the gas project has been 100%.   » more information

2021-02-05

Summary of project performance Up to 2021-02-05

AJS Steel Company’s has achieved a progress of 85.21% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 92.03%. Also, this project has achieved progressed 99.51% in construction and 70.22% in erection activities. Also, there has been 97.68% progress in the Electricity Substation Project, and achieve progress 68.80% in the RO department and also progress in the gas project has been 100%.

» more information

2021-01-15

Summary of project performance Up to 2021-01-15

AJS Company’s has achieved a progress of 84.49% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 91.65%. Also, this project has achieved progressed 99.37% in construction and 68% in erection activities. Also, there has been 97.65% progress in the Electricity Substation Project, and achieve progress 66.72% in the RO department and also progress in the gas project has been 100%.

» more information

2021-01-08

Summary of project performance Up to 2021-01-08

AJS Company’s has achieved a progress of 84.31% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 91.64%. Also, this project has achieved progressed 99.37% in construction and 67.28% in erection activities. Also, there has been 97.65% progress in the Electricity Substation Project, and achieve progress 66.09% in the RO department and also progress in the gas project has been 100%.   » more information

2021-01-01

Summary of project performance Up to 2021-01-01

AJS Company’s has achieved a progress of 83.94% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 91.63%. Also, this project has achieved progressed 99.34% in construction and 65.69% in erection activities. Also, there has been 97.64% progress in the Electricity Substation Project, and achieve progress 65.95% in the RO department and also progress in the gas project has been 100%.   » more information

2021-11-20

Summary of project performance Up to  2021-11-20

AJS Company’s has achieved a progress of 82.65% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 91.51%. Also, this project has achieved progressed 98.73% in construction and 60.90% in erection activities. Also, there has been 97.36% progress in the Electricity Substation Project, and achieve progress 64.99% in the RO department and also progress in the gas project has been 100%.   » more information

2021-10-09

Summary of project performance Up to  2021-10-09

AJS Company’s has achieved a progress of 80.76% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 90.26%. Also, this project has achieved progressed 98.58% in construction and 55.41% in erection activities. Also, there has been 97.02% progress in the Electricity Substation Project, and achieve progress 64.03% in the RO department and also progress in the gas project has been 100%.   » more information

2021-10-02

Summary of project performance Up to 2021-10-02

AJS Company’s has achieved a progress of 80.47% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 90.01%. Also, this project has achieved progressed 98.54% in construction and 54.50% in erection activities. Also, there has been 96.97% progress in the Electricity Substation Project, and achieve progress 63.71% in the RO department and also progress in the gas project has been 100%.

»more information

2021-09-25

Summary of project performance Up to 2021-09-25

AJS Company’s has achieved a progress of 80.03% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 90 %. Also, this project has achieved progressed 98.50% in construction and 53.90% in erection activities. Also, there has been 96.91% progress in the Electricity Substation Project, and achieve progress 63.71% in the RO department and also progress in the gas project has been 100%.

» more information

2021-09-18

Summary of project performance Up to 2021-09-18

AJS Company’s has achieved a progress of 79.92% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 89.62 %. Also, this project has achieved progressed 98.39% in construction and 53.27% in erection activities. Also, there has been 96.85% progress in the Electricity Substation Project, and achieve progress 63.57% in the RO department and also progress in the gas project has been 100%.   » more information

2021-09-11

Summary of project performance Up to 2021-09-11

AJS Company’s has achieved a progress of 79.63% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 89.59 %. Also, this project has achieved progressed 98.36% in construction and 52.06% in erection activities. Also, there has been 96.79% progress in the Electricity Substation Project, and achieve progress 63.42% in the RO department and also progress in the gas project has been 100%.   » more information

2021-09-04

Summary of project performance Up to 2021-09-04

AJS Company’s has achieved a progress of 79.19% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.53%, and in the procurement  the progress has been 89.20 %. Also, this project has achieved progressed 98.32% in construction and 51.00% in erection activities. Also, there has been 96.70% progress in the Electricity Substation Project, and achieve progress 62.90% in the RO department and also progress in the gas project has been 100%.   » more information

2021-08-28

Summary of project performance Up to 2021-08-28

AJS Company’s has achieved a progress of 78.91% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.48%, and in the procurement  the progress has been 88.84 %. Also, this project has achieved progressed 98.25% in construction and 50.62% in erection activities. Also, there has been 96.62% progress in the Electricity Substation Project, and achieve progress 62.66% in the RO department and also progress in the gas project has been 100%.   » more information

2021-08-21

Summary of project performance Up to 2021-08-21

AJS Company’s has achieved a progress of 78.57% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.48%, and in the procurement  the progress has been 88.77 %. Also, this project has achieved progressed 98.16% in construction and 49.37% in erection activities. Also, there has been 96.59% progress in the Electricity Substation Project, and achieve progress 62.29% in the RO department and also progress in the gas project has been 100%.

» more information

2021-08-14

Summary of project performance Up to 2021-08-14

AJS Company’s has achieved a progress of 78.39% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.48%, and in the procurement  the progress has been 88.74 %. Also, this project has achieved progressed 98.06% in construction and 48.74% in erection activities. Also, there has been 96.39% progress in the Electricity Substation Project, and achieve progress 62.16% in the RO department and also progress in the gas project has been 100%.

» more information

2021-08-07

Summary of project performance Up to 2021-08-07

AJS Company’s has achieved a progress of 78.15% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.48%, and in the procurement  the progress has been 88.61 %. Also, this project has achieved progressed 97.96% in construction and 48.04% in erection activities. Also, there has been 96.21% progress in the Electricity Substation Project, and achieve progress 61.89% in the RO department and also progress in the gas project has been 100%.   » more information

2021-07-31

Summary of project performance Up to 2021-07-31

AJS Company’s has achieved a progress of 77.72% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.48%, and in the procurement  the progress has been 88.50 %. Also, this project has achieved progressed 97.82% in construction and 76.51% in erection activities. Also, there has been 96.05% progress in the Electricity Substation Project, and achieve progress 61.51% in the RO department and also progress in the gas project has been 100%.   » more information

2021-07-31

Summary of project performance Up to 2021-07-31

AJS Company’s has achieved a progress of 77.72% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.48%, and in the procurement  the progress has been 88.50 %. Also, this project has achieved progressed 97.82% in construction and 76.51% in erection activities. Also, there has been 96.05% progress in the Electricity Substation Project, and achieve progress 61.51% in the RO department and also progress in the gas project has been 100%.

» more information

2021-07-24

Summary of project performance Up to 2021-07-24

AJS Company’s has achieved a progress of 77.34% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.48%, and in the procurement  the progress has been 88.48 %. Also, this project has achieved progressed 97.68% in construction and 45.04% in erection activities. Also, there has been 95.93% progress in the Electricity Substation Project, and achieve progress 61.45% in the RO department and also progress in the gas project has been 100%.  .

» more information

2021-07-17

Summary of project performance Up to 2021-07-17

AJS Company’s has achieved a progress of 76.09% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.27%, and in the procurement  the progress has been 86.78 %. Also, this project has achieved progressed 97.65% in construction and 43.22% in erection activities. Also, there has been 95.38% progress in the Electricity Substation Project, and achieve progress 60.69% in the RO department and also progress in the gas project has been 100%.   » more information

2021-07-10

Summary of project performance Up to 2021-07-10

AJS Company’s has achieved a progress of 75.83% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.27%, and in the procurement  the progress has been 86.69 %. Also, this project has achieved progressed 97.62% in construction and 42.34% in erection activities. Also, there has been 95.38% progress in the Electricity Substation Project, and achieve progress 60.69% in the RO department and also progress in the gas project has been 100%.   » more information

2021-07-03

Summary of project performance Up to 2021-07-03

AJS Company’s has achieved a progress of 75.48% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.27%, and in the procurement  the progress has been 86.65 %. Also, this project has achieved progressed 97.57% in construction and 40.92% in erection activities. Also, there has been 95.36% progress in the Electricity Substation Project, and achieve progress 60.43% in the RO department and also progress in the gas project has been 100%.   » more information

2021-06-26

Summary of project performance Up to 2021-06-26

AJS Company’s has achieved a progress of 75.19% in total, the details of the progress of the first phase of the casting project in the Engineering with 99.27%, and in the procurement  the progress has been 86.42 %. Also, this project has achieved progressed 97.54% in construction and 40.14% in erection activities. Also, there has been 95.34% progress in the Electricity Substation Project, and achieve progress 60.17% in the RO department and also progress in the gas project has been 100%.   » more information

2021-06-19

Summary of project performance Up to 2021-06-19

AJS Company’s has achieved a progress of 74.72% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.99%, and in the procurement  the progress has been 85.75 %. Also, this project has achieved progressed 97.48% in construction and 39.65% in erection activities. Also, there has been 95.17% progress in the Electricity Substation Project, and achieve progress 60.06% in the RO department and also progress in the gas project has been 100%.   » more information

2021-06-12

Summary of project performance Up to 2021-06-12

AJS Company’s has achieved a progress of 74.36% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.99%, and in the procurement  the progress has been 85.35 %. Also, this project has achieved progressed 97.44% in construction and 38.93% in erection activities. Also, there has been 95.17% progress in the Electricity Substation Project, and achieve progress 60.06% in the RO department and also progress in the gas project has been 100%.   » more information

2021-06-12

Summary of project performance Up to 2021-06-12

AJS Company’s has achieved a progress of 73.94% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.99%, and in the procurement  the progress has been 85.02 %. Also, this project has achieved progressed 97.26% in construction and 37.95% in erection activities. Also, there has been 94.93% progress in the Electricity Substation Project, and achieve progress 59.54% in the RO department and also progress in the gas project has been 100%.   » more information

2021-05-29

Summary of project performance Up to 2021-05-29

AJS Company’s has achieved a progress of 73.60% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.99%, and in the procurement  the progress has been 84.73 %. Also, this project has achieved progressed 97.02% in construction and 37.12% in erection activities. Also, there has been 94.77% progress in the Electricity Substation Project, and achieve progress 59.02% in the RO department and also progress in the gas project has been 100%.  .

» more information

2021-05-22

Summary of project performance Up to 2021-05-22

AJS Company’s has achieved a progress of 73.09% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.95%, and in the procurement  the progress has been 83.97 %. Also, this project has achieved progressed 97.01% in construction and 36.66% in erection activities. Also, there has been 94.66% progress in the Electricity Substation Project, and achieve progress 58.75% in the RO department and also progress in the gas project has been 100%.   » more information

2021-05-15

Summary of project performance Up to  2021-05-15

AJS Company’s has achieved a progress of 72.83% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.95%, and in the procurement  the progress has been 83.76 %. Also, this project has achieved progressed 96.94% in construction and 36.03% in erection activities. Also, there has been 94.65% progress in the Electricity Substation Project, and achieve progress 58.59% in the RO department and also progress in the gas project has been 100%.

» more information

2021-05-08

Summary of project performance Up to 2021-05-08

AJS Company’s has achieved a progress of 72.50% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.95%, and in the procurement  the progress has been 83.53 %. Also, this project has achieved progressed 96.64% in construction and 35.37% in erection activities. Also, there has been 94.59% progress in the Electricity Substation Project, and achieve progress 58.34% in the RO department and also progress in the gas project has been 100%.

» more information

2021-05-01

Summary of project performance Up to 2021-05-01

AJS Company’s has achieved a progress of 72.33% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.95%, and in the procurement  the progress has been 83.43 %. Also, this project has achieved progressed 96.59% in construction and 35.87% in erection activities. Also, there has been 94.5% progress in the Electricity Substation Project, and achieve progress 58.03% in the RO department and also progress in the gas project has been 100%.   » more information

2021-04-24

Summary of project performance Up to 2021-04-24

AJS Company’s has achieved a progress of 72.10% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.95%, and in the procurement  the progress has been 83.21 %. Also, this project has achieved progressed 96.48% in construction and 34.41% in erection activities. Also, there has been 94.41% progress in the Electricity Substation Project, and achieve progress 55.70% in the RO department and also progress in the gas project has been 100%.  .

» more information

2021-04-13

Summary of project performance Up to 2021-04-13

AJS Company’s has achieved a progress of 71.20% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.74%, and in the procurement  the progress has been 82.12 %. Also, this project has achieved progressed 96.13% in construction and 32.96% in erection activities. Also, there has been 94.23% progress in the Electricity Substation Project, and achieve progress 53.18% in the RO department and also progress in the gas project has been 100%.   » more information

2021-03-06

Summary of project performance Up to 2021-03-06

AJS Company’s has achieved a progress of 71.03% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.74%, and in the procurement  the progress has been 81.99 %. Also, this project has achieved progressed 96.09% in construction and 32.69% in erection activities. Also, there has been 94.13% progress in the Electricity Substation Project, and achieve progress 52.52% in the RO department and also progress in the gas project has been 100%.

» more information

2021-02-27

Summary of project performance Up to 2021-02-27

AJS Company’s has achieved a progress of 70.72% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.74%, and in the procurement  the progress has been 81.91 %. Also, this project has achieved progressed 95.31% in construction and 32.2% in erection activities. Also, there has been 93.95% progress in the Electricity Substation Project, and achieve progress 52.09% in the RO department and also progress in the gas project has been 100%.

» more information

2021-02-19

Summary of project performance Up to  2021-02-19

AJS Company’s has achieved a progress of 70.40% in total, the details of the progress of the first phase of the casting project in the Engineering with 98.59%, and in the procurement  the progress has been 81.70 %. Also, this project has achieved progressed 94.75% in construction and 31.75% in erection activities. Also, there has been 93.87% progress in the Electricity Substation Project, and achieve progress 51.63% in the RO department and also progress in the gas project has been 100%.   » more information

2021-02-13

Summary of project performance Up to  2021-02-13

AJS Company’s has achieved a progress of 70.15 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.59%, and in the procurement  the progress has been 80.96 %. Also, this project has achieved progressed 94.29% in construction and 31.11% in erection activities. Also, there has been 93.78% progress in the Electricity Substation Project, and achieve progress 51.20% in the RO department and also progress in the gas project has been 100%.

» more information

2021-02-06

Summary of project performance Up to  2021-02-06

AJS Company’s has achieved a progress of 69.58 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.59%, and in the procurement  the progress has been 80.96 %. Also, this project has achieved progressed 93.97% in construction and 30.20% in erection activities. Also, there has been 93.60% progress in the Electricity Substation Project, and achieve progress 50.92% in the RO department and also progress in the gas project has been 100%.

» more information

2021-01-30

Summary of project performance Up to  2021-01-30

AJS Company’s has achieved a progress of 69 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.59%, and in the procurement  the progress has been 80.57 %. Also, this project has achieved progressed 93.14% in construction and 29.77% in erection activities. Also, there has been 93.47% progress in the Electricity Substation Project, and achieve progress 50.79% in the RO department and also progress in the gas project has been 100%.

» more information

2021-01-23

Summary of project performance Up to  2021-01-23

AJS Company’s has achieved a progress of 68.74 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.58%, and in the procurement  the progress has been 80.51 %. Also, this project has achieved progressed 92.73% in construction and 28.79% in erection activities. Also, there has been 93.73 % progress in the Electricity Substation Project, and achieve progress 50.37% in the RO department and also progress in the gas project has been 99.72%.   » more information

2021-01-16

Summary of project performance Up to  2021-01-16

AJS Company’s has achieved a progress of 68.30 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.51%, and in the procurement  the progress has been 79.94 %. Also, this project has achieved progressed 92.45% in construction and 28.30% in erection activities. Also, there has been 93.24 % progress in the Electricity Substation Project, and achieve progress 50.12% in the RO department and also progress in the gas project has been 99.63%.   »more information

2021-01-09

Summary of project performance Up to  2021-01-09

AJS Company’s has achieved a progress of 67.98 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.38%, and in the procurement  the progress has been 79.94 %. Also, this project has achieved progressed 91.93% in construction and 27.39% in erection activities. Also, there has been 92.81 % progress in the Electricity Substation Project, and achieve progress 49.76% in the RO department and also progress in the gas project has been 99.63%.   » more information

2021-01-02

Summary of project performance Up to  2021-01-02

AJS Company’s has achieved a progress of 67.58 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.38%, and in the procurement  the progress has been 79.45 %. Also, this project has achieved progressed 91.76% in construction and 26.85% in erection activities. Also, there has been 92.51 % progress in the Electricity Substation Project, and achieve progress 49.30% in the RO department and also progress in the gas project has been 99.63%.   »more information

2020-12-26

Summary of project performance Up to  2020-12-26

AJS Company’s has achieved a progress of 67.31 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.38%, and in the procurement  the progress has been 79.18 %. Also, this project has achieved progressed 91.53% in construction and 26.45% in erection activities. Also, there has been 92.24 % progress in the Electricity Substation Project, and achieve progress 48.77% in the RO department and also progress in the gas project has been 99.63%.   » more information

2020-12-19

Summary of project performance Up to  2020-12-19

AJS Company’s has achieved a progress of 67.07 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.38%, and in the procurement  the progress has been 78.96 %. Also, this project has achieved progressed 91.06% in construction and 26.24% in erection activities. Also, there has been 90.99 % progress in the Electricity Substation Project, and achieve progress 48.14% in the RO department and also progress in the gas project has been 99.63%.   » more information

2020-12-12

Summary of project performance Up to  2020-12-12

AJS Company’s has achieved a progress of 66.87 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.38%, and in the procurement  the progress has been 78.79 %. Also, this project has achieved progressed 90.60% in construction and 26.12% in erection activities. Also, there has been 83.10 % progress in the Electricity Substation Project, and achieve progress 46.09% in the RO department and also progress in the gas project has been 99.63%.   »more information

2020-12-05

Summary of project performance Up to  2020-12-05

AJS Company’s has achieved a progress of 66.53 % in total, the details of the progress of the first phase of the casting project in the Engineering with 98.38%, and in the procurement  the progress has been 78.32 %. Also, this project has achieved progressed 90.26% in construction and 25.94% in erection activities. Also, there has been 82.60 % progress in the Electricity Substation Project, and achieve progress 45.7% in the RO department and also progress in the gas project has been 99.63%.   » more information

2020-11-28

Summary of project performance Up to  2020-11-28

AJS Company’s has achieved a progress of 66.33 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.57%, and in the procurement  the progress has been 78.17 %. Also, this project has achieved progressed 90.15% in construction and 25.63% in erection activities. Also, there has been 82.11 % progress in the Electricity Substation Project, and achieve progress 44.25% in the RO department and also progress in the gas project has been 99.63%.   » more information

2020-11-21

Summary of project performance Up to  2020-11-21

AJS Company’s has achieved a progress of 66.22 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.57%, and in the procurement  the progress has been 78.09 %. Also, this project has achieved progressed 89.96% in construction and 25.50% in erection activities. Also, there has been 81.93 % progress in the Electricity Substation Project, and achieve progress 41.95% in the RO department and also progress in the gas project has been 99.63%.   »more information

2020-11-14

Summary of project performance Up to 2020-11-14

AJS Company’s has achieved a progress of 66.14 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.57%, and in the procurement  the progress has been 78.09 %. Also, this project has achieved progressed 89.81% in construction and 25.30% in erection activities. Also, there has been 81.58 % progress in the Electricity Substation Project, and achieve progress 37.55% in the RO department and also progress in the gas project has been 99.63%.   » more information

2020-11-07

Summary of project performance Up to 2020-11-07

AJS Company’s has achieved a progress of 65.61 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.57%, and in the procurement  the progress has been 77.26 %. Also, this project has achieved progressed 89.45% in construction and 25.05% in erection activities. Also, there has been 81.35 % progress in the Electricity Substation Project, and achieve progress 36.61% in the RO department and also progress in the gas project has been 99.45%.   » more information

2020-10-31

Summary of project performance Up to 2020-10-31

AJS Company’s has achieved a progress of 65.43 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.57%, and in the procurement  the progress has been 77.03 %. Also, this project has achieved progressed 89.29% in construction and 24.85% in erection activities. Also, there has been 81.18 % progress in the Electricity Substation Project, and achieve progress 35.08% in the RO department and also progress in the gas project has been 99.39%.   » more information

2020-10-24

Summary of project performance Up to 2020-10-24

AJS Company’s has achieved a progress of 64.51 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.19%, and in the procurement  the progress has been 75.42 %. Also, this project has achieved progressed 89.08% in construction and 24.50% in erection activities. Also, there has been 80.92 % progress in the Electricity Substation Project, and achieve progress 34.09% in the RO department and also progress in the gas project has been 98.59%.   » more information

2020-10-17

Summary of project performance Up to 2020-10-17

AJS Company’s has achieved a progress of 64.33 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.19%, and in the procurement  the progress has been 75.17 %. Also, this project has achieved progressed 89 % in construction and 24.29% in erection activities. Also, there has been 80.73 % progress in the Electricity Substation Project, and achieve progress 34.01% in the RO department and also progress in the gas project has been 98.59%.   »more information

2020-10-10

Summary of project performance Up to 2020-10-10

AJS Company’s has achieved a progress of 64.11 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.19%, and in the procurement  the progress has been 74.93 %. Also, this project has achieved progressed 88.91 % in construction and 23.93% in erection activities. Also, there has been 74.28 % progress in the Electricity Substation Project, and achieve progress 33.3% in the RO department and also progress in the gas project has been 95.26%.   » more information

2020-10-03

Summary of project performance Up to  2020-10-03

AJS Company’s has achieved a progress of 63.70 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 74.36 %. Also, this project has achieved progressed 88.57 % in construction and 23.11% in erection activities. Also, there has been 73.65 % progress in the Electricity Substation Project, and achieve progress 32.42% in the RO department and also progress in the gas project has been 92.28%.   » more information

2020-09-26

Summary of project performance Up to 2020-09-26

AJS Company’s has achieved a progress of 63.30 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 73.79 %. Also, this project has achieved progressed 88.57 % in construction and 23.11% in erection activities. Also, there has been 73.25 % progress in the Electricity Substation Project, and achieve progress 31.96% in the RO department and also progress in the gas project has been 88.98%.   » بیشتر بدانم

2020-09-19

AJS Company’s has achieved a progress of 63.10 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 73.58 %. Also, this project has achieved progressed 88.38 % in construction and 22.81% in erection activities. Also, there has been 73.08 % progress in the Electricity Substation Project, and achieve progress 30.99% in the RO department and also progress in the gas project has been 88.98%.   » more information

2020-09-5

Summary of project performance Up to  2020-09-5

AJS Company’s has achieved a progress of 62.41 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 72.57 %. Also, this project has achieved progressed 87.97 % in construction and 22.27% in erection activities. Also, there has been 72.01 % progress in the Electricity Substation Project, and achieve progress 27.89% in the RO department and also progress in the gas project has been 88.98%.   » more information

2020-08-29

Summary of project performance Up to  2020-08-29

AJS Company’s has achieved a progress of 62.05 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 72.24 %. Also, this project has achieved progressed 87.65 % in construction and 22.68% in erection activities. Also, there has been 72.01 % progress in the Electricity Substation Project, and achieve progress 27.89% in the RO department and also progress in the gas project has been 88.98%.   » more information

2020-08-22

AJS Company’s has achieved a progress of 61.56 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 71.57 %. Also, this project has achieved progressed 87.29 % in construction and 21.27% in erection activities. Also, there has been 71.10 % progress in the Electricity Substation Project, and achieve progress 27.61% in the RO department and also progress in the gas project has been 87.19%.   » more information

2020-08-15

Summary of project performance Up to  2020-08-15

AJS Company’s has achieved a progress of 61.45 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 71.57 %. Also, this project has achieved progressed 87.01 % in construction and 21.04% in erection activities. Also, there has been 70.83 % progress in the Electricity Substation Project, and achieve progress 27.07% in the RO department and also progress in the gas project has been 85.90%.   » more information

2020-08-08

Summary of project performance Up to 2020-08-08

AJS Company’s has achieved a progress of 61.03 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 71.51 %. Also, this project has achieved progressed 86.87 % in construction and 20.63% in erection activities. Also, there has been 70.32 % progress in the Electricity Substation Project, and achieve progress 25.98% in the RO department and also progress in the gas project has been 83.26%. » more information

2020-08-01

Summary of project performance Up to 2020-08-01

AJS Company’s has achieved a progress of 61.01 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 71.41 %. Also, this project has achieved progressed 86.62 % in construction and 20.28% in erection activities. Also, there has been 69.85 % progress in the Electricity Substation Project, and achieve progress 24.80% in the RO department and also progress in the gas project has been 77.96%.   »more information

2020-07-25

Summary of project performance Up to  2020-07-25

AJS Company’s has achieved a progress of 60.78 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 71.27 %. Also, this project has achieved progressed 86.25 % in construction and 19.39% in erection activities. Also, there has been 69.44 % progress in the Electricity Substation Project, and achieve progress 23.53% in the RO.   » more information

2020-07-18

Summary of project performance Up to  2020-07-18

AJS Company’s has achieved a progress of 60.11 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 70.39 %. Also, this project has achieved progressed 86.02 % in construction and 18.54% in erection activities. Also, there has been 68.98 % progress in the Electricity Substation Project, and achieve progress 22.93% in the RO.   » more information

2020-07-11

Summary of project performance Up to  2020-07-11

AJS Company’s has achieved a progress of 59.75 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 70.07 %. Also, this project has achieved progressed 85.83 % in construction and 17.78% in erection activities. Also, there has been 68.01 % progress in the Electricity Substation Project, and achieve progress 22.10% in the RO » more information

2020-07-04

Summary of project performance Up to  2020-07-04

AJS Company’s has achieved a progress of 59.54 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.12%, and in the procurement  the progress has been 69.84 %. Also, this project has achieved progressed 85.67 % in construction and 17.05% in erection activities. Also, there has been 67.59 % progress in the Electricity Substation Project, and achieve progress 20.71% in the RO.   » more information

2020-06-30

Summary of project performance Up to  2020-06-30

AJS Company’s has achieved a progress of 59.18 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.1%, and in the procurement  the progress has been 69.48 %. Also, this project has achieved progressed 85.46 % in construction and 16.89% in erection activities. Also, there has been 66.51 % progress in the Electricity Substation Project, and achieve progress 13.50% in the RO.   » more information

2020-06-23

Summary of project performance Up to 2020-06-23

AJS Company’s has achieved a progress of 58.98 % in total, the details of the progress of the first phase of the casting project in the Engineering with 97.1%, and in the procurement  the progress has been 69.48 %. Also, this project has achieved progressed 85.06 % in construction and 16.34% in erection activities. Also, there has been 65.96 % progress in the Electricity Substation Project, and achieve progress 12.75% in the RO.   » more information

2020-06-16

Summary of project performance Up to 2020-06-16

AJS Company’s has achieved a progress of 56.59 % in total, the details of the progress of the first phase of the casting project in the Engineering with 96.2%, and in the procurement  the progress has been 65.15 %. Also, this project has achieved progressed 84.51 % in construction and 15.66% in erection activities. Also, there has been 64.49 % progress in the Electricity Substation Project, and achieve progress 11.80% in the RO.   » more information

2020-06-09

Summary of project performance Up to 2020-06-09

AJS Company’s has achieved a progress of 56.04 % in total, the details of the progress of the first phase of the casting project in the Engineering with 96.2%, and in the procurement  the progress has been 64.9 %. Also, this project has achieved progressed 83.36 % in construction and 14.79% in erection activities. Also, there has been 62.18 % progress in the Electricity Substation Project, and achieve progress 11.33% in the RO.   » more information

2020-06-02

Summary of project performance Up to 2020-06-02

AJS Company’s has achieved a progress of 55.8 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 64.9 %. Also, this project has achieved progressed 83 % in construction and 14.2 % in erection activities.

» more information

020-05-09

Summary of project performance Up to 2020-05-09

AJS Company’s has achieved a progress of 54.98 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 63.76 %. Also, this project has achieved progressed 82.29 % in construction and 13.51 % in erection activities.

»more information

2020-05-02

Summary of project performance Up to 2020-05-02

AJS Company’s has achieved a progress of 54.18 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 63.57 %. Also, this project has achieved progressed 81.03 % in construction and 11.65 % in erection activities.

» more information

2020-04-18

Summary of project performance Up to 2020-04-18

AJS Company’s has achieved a progress of 53.76 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 63.05 %. Also, this project has achieved progressed 80.72 % in construction and 11.15 % in erection activities.

»more information

2020-04-11

Summary of project performance Up to  2020-04-11

AJS Company’s has achieved a progress of 52.94 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 61.94 %. Also, this project has achieved progressed 80.40 % in construction and 10.19 % in erection activities.

» more information

2020-04-04

AJS Company’s has achieved a progress of 52.52 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 61.29 %. Also, this project has achieved progressed 80.40 % in construction and 9.74 % in erection activities.

more information

2019-03-06

Summary of project performance Up to 2019-03-06

AJS Company’s has achieved a progress of 51.66 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 60.22 %. Also, this project has achieved progressed 79.46 % in construction and 9.06 % in erection activities.

more information 

2019-02-19

Summary of project performance Up to 2019-02-19

AJS Company’s has achieved a progress of 51.26 % in total, the details of the progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 60 %. Also, this project has achieved progressed 78.46 % in construction and 8.66 % in erection activities.

.

2019-02-11

Summary of project performance Up to 2019-02-11

AJS Company’s has achieved a progress of the first phase of the casting project in the Engineering with 95.65%, and in the procurement  the progress has been 59.84 % and in civil work has been achieve  progress to 39.78 .also in erection activities achieve to progress 7.9 %.

2019-01-20

Summary of project performance Up to 2019-01-20

AJS Company’s has achieved a progress of the first phase of the casting project in the Engineering with 90.65%, and in the procurement  the progress has been 33.53 % and in civil work has been achieve  progress to 25.80 .also in erection and commissioning activities achieve to progress 0.17 %.

2018-12-21

Summary of project performance Up to 2018-12-21

AJS Company’s has achieved a progress of 44.59 % in total the first phase of the casting project in the Engineering with 90.65%, and in the procurement  the progress has been 33.53 % and in civil work has been achieve  progress to 25.80 .also in erection and commissioning activities achieve to progress 0.17 %.

.

C1
Dust collector
Metal (several tons) 2040
Piping 6800 inches
Cabling 17000 meters
Duration of the job 6 months
Contractor: MMT
C2
Furnace
Metal (several tons) 4960
Piping 13000 inches
Cabling 61090 meters
Duration of the job 10 months
Contractor: EOS
C3
CCM
Metal (several tons) 2408
Piping 23000 inches
Cabling 36075 meters
Duration of the job 12 months
Contractor: MMTE